Clothing Production Calendar: When to Start Sampling and Bulk Production for Each Season

The most common reason a small brand misses a season is not a design problem. It is a calendar problem. Sampling took longer than expected, the fabric was not ready, or the order landed in the factory’s busiest month — and by the time the garments arrived, the season was already half over.

This guide gives you a production calendar you can plan around: how long each stage actually takes, when to start for each season, and the dates that catch first-time brands out. It is written for a small brand ordering in small batches, not for a large retailer with a year-long planning cycle, so the numbers are realistic for an order of 80–100 pieces per style per color.

How Long Each Stage Takes

Before you can plan a season, you need to know how long each step takes. These are the standard times we work to, once the design and the fabric are confirmed.

  • Sampling: 7–14 days. Seven days is only realistic for simple styles such as T-shirts and camisoles without printing or embroidery. A style with a print, embroidery, or a special trim needs the full 7–14 days, and a second sample round adds another 7–14 days.
  • Pattern, grading, and fabric sourcing: usually inside the sampling period, but a special fabric or a custom print can add a week or more if the mill has to dye or print it.
  • Bulk production: 4–5 weeks. Complex styles, special fabrics, and pre-holiday orders need separate confirmation, and they can take longer.
  • Quality control and packing: usually a few days, inside the bulk production window, unless a re-inspection is needed.
  • Shipping: depends on the method and the destination, and the exact freight is confirmed after bulk production is complete. DDP shipping to the US can be arranged.

Add the stages together and a realistic timeline from first sample to goods in hand is roughly two to three months, depending on how many sample rounds you need and how fast you confirm each step. If you confirm the sample quickly, the order moves quickly. If the sample sits unconfirmed for three weeks, the whole schedule shifts by three weeks. For a fuller explanation of sampling time, see our garment sampling guide.

Spring: Start in November

Spring collections need to be in hand by February or March, which means sampling should start in November. That is earlier than most first-time brands expect, and it is the season that catches the most people out, because November feels like the end of the year, not the start of spring.

A spring timeline looks like this: send your designs and fabric choices in November, confirm the samples by December or early January, start bulk production in January, and receive the goods in February. The risk in this window is the Chinese New Year holiday, which falls in January or February and closes most factories for two to three weeks. If your bulk production runs into the holiday, it will stop and restart after the holiday, so plan to finish production before the holiday starts, or start it after the holiday ends. Ask the factory for the holiday dates when you place the order — they are published a year in advance.

Spring fabrics are usually lighter — cotton poplin, linen blends, light jersey — and light fabrics are often in stock, so fabric sourcing is less of a delay than in other seasons. The main risk is the holiday, not the fabric.

Summer: Start in February

Summer collections need to be in hand by April or May, which means sampling should start in February. That is just after the Chinese New Year holiday, so factories are back to full capacity and the schedule is more predictable than in the spring window.

A summer timeline: send your designs in February, confirm samples in March, start bulk in March or April, and receive goods in April or May. Summer styles are usually simple — T-shirts, camisoles, light dresses, shorts — and simple styles sample faster. That is also why 7-day sampling is sometimes achievable in summer: a T-shirt or a camisole without printing or embroidery is the kind of style that can be sampled in a week. Our sampling time guide explains which styles qualify.

The risk in summer is not the holiday but the heat and the volume. Summer is a busy season for factories, and a late order can be pushed back if the factory’s line is full. Order early in the window, not at the end of it, and confirm the sample quickly so your bulk production is booked into the schedule.

Autumn: Start in May

Autumn collections need to be in hand by August or September, which means sampling should start in May. Autumn styles are usually heavier than summer styles — midweight jersey, French terry, light wool blends — and heavier fabrics take longer to source, so fabric planning matters more in this window.

An autumn timeline: send your designs in May, confirm samples in June, start bulk in June or July, and receive goods in August. The key date to watch is the summer holiday period in the factory’s region, and the fact that autumn orders often overlap with the start of the winter production window, so the factory’s capacity is shared between two seasons. If you are ordering for both autumn and winter, tell the factory at the start, so the two orders can be planned together.

Autumn is also the season where a second sample round is most common, because the fit of a heavier garment is harder to judge from a single sample. Budget for two sample rounds in your timeline — if you only need one, you will be ahead of schedule; if you need two and did not plan for it, you will be late.

Winter: Start in August

Winter collections need to be in hand by October or November, which means sampling should start in August. Winter styles are the heaviest and the most complex — hoodies, coats, thick knitwear — and they take the longest to sample and to sew. Our hoodie manufacturing guide explains why a heavyweight hoodie needs more time than a summer T-shirt.

A winter timeline: send your designs in August, confirm samples in September, start bulk in September or October, and receive goods in October or November. The risk in this window is the National Day holiday in early October, which closes factories for about a week. It is a shorter holiday than Chinese New Year, but it still interrupts production, so plan around it. The other risk is fabric: heavy fabrics and special trims — a thick fleece, a water-resistant coating, a metal zip — often have a longer lead time from the mill, so confirm the fabric early, before the sample is finished.

Winter is also the season where a minimum order matters most. A heavyweight hoodie uses more fabric per piece and costs more to make, so the unit price is higher than for a summer T-shirt. The minimum is still 80–100 pieces per style per color, with some styles from 50 pieces, but the total order value is higher, so plan the quantities carefully. Our MOQ guide explains how minimums work for small batches.

Holidays and Factory Shutdowns: The Dates That Catch Brands Out

There are two holidays that matter for production planning, and both are worth marking on your calendar a year in advance.

Chinese New Year. Usually in January or February, and the longest shutdown of the year. Factories close for two to three weeks, and the weeks before and after the holiday are also busy, because every brand is trying to finish before the shutdown or restart after it. If your order has to ship before the holiday, it must be finished well before it — not the day before.

National Day. Early October, about a week. Shorter, but it still stops production, and it falls in the middle of the winter production window, so it is easy to forget.

There are also shorter public holidays throughout the year, and the factory may close for a few days around them. The practical rule is simple: ask the factory for the holiday calendar when you place the order, and build a week of buffer into your timeline for any order that runs across a holiday. A week of buffer costs nothing if you do not need it, and it saves the season if you do.

Building Your Own Calendar

A production calendar is not complicated. It is a table with four columns: the season, the date you need the goods, the date sampling should start, and the date bulk production should start. Work backwards from the date you need the goods, subtract the bulk production time (4–5 weeks), subtract the sampling time (7–14 days, more if you need two sample rounds), and add a week of buffer for holidays and delays. That gives you the date to send your designs.

Three habits make the calendar work. First, send your designs earlier than you think you need to — the factory can always hold a confirmed sample until you are ready, but it cannot make up lost weeks. Second, confirm samples quickly. A sample that sits unconfirmed for two weeks pushes the whole schedule by two weeks, and the factory cannot book your bulk production until the sample is approved. Third, plan the whole year at once. If you know you want a spring collection and a summer collection, send both briefs together, so the factory can plan the capacity for both, rather than treating each one as a surprise.

If you want help planning a specific season, contact us with the date you need the goods and the styles you are planning, and we will work backwards from your date and confirm the sampling and production schedule for your order.

FAQs

How far in advance should I start sampling for a new season?

Work backwards from the date you need the goods. Subtract 4–5 weeks for bulk production, 7–14 days for sampling (more if you need two sample rounds), and a week of buffer. As a rule of thumb: spring, start in November; summer, start in February; autumn, start in May; winter, start in August.

How long does sampling take?

Sampling usually takes 7–14 days once fabrics and trims are confirmed. Seven days is only realistic for simple styles such as T-shirts and camisoles without printing or embroidery. A second sample round adds another 7–14 days, so budget for it in your calendar if the style is complex.

How long does bulk production take?

Bulk production usually takes 4–5 weeks. Complex styles, special fabrics, and pre-holiday orders need separate confirmation. Quality control and packing are usually inside that window, unless a re-inspection is needed.

What is the biggest risk to my production calendar?

Confirming the sample late. The factory cannot book your bulk production until the sample is approved, so a sample that sits unconfirmed for three weeks pushes the whole schedule by three weeks. The second biggest risk is a holiday — Chinese New Year in January or February, and National Day in early October — falling in the middle of your production window.

Does Chinese New Year affect my order?

Yes, if your order runs across it. Factories close for two to three weeks, and the weeks before and after are busy. Ask the factory for the holiday dates when you place the order, and plan to finish production before the holiday or start it after.

Can I order for two seasons at once?

Yes, and it helps the factory plan capacity. If you know you want an autumn and a winter collection, send both briefs together, so the two orders can be scheduled together rather than competing for the same production line.

What if I miss the start date for a season?

Tell the factory the date you need the goods, and ask what is still possible. A simpler style, an in-stock fabric, or a smaller first order may still be feasible. What is not possible is compressing sampling and bulk production into a few days — the stages take the time they take, and rushing them usually means a worse sample.

Working with Laiwen Clothing

Laiwen Clothing is a small-batch OEM/ODM garment manufacturer in Humen, Dongguan, China, making womenswear, childrenswear, and family wear for overseas startup brands. We work from your design drawing, reference image, physical sample, or tech pack — sourcing fabric and trims, making patterns, sampling, grading, producing bulk, and handling quality control and packing. Our usual minimum is 80–100 pieces per style per color, with some styles from 50 pieces, sampling in 7–14 days and bulk production in 4–5 weeks. If you have a season in mind, contact us with the date you need the goods, and we will work backwards from your date and confirm the sampling and production schedule for your order.